TRACK-111: DAL Test Suite + CI Activation (Steps 3–4)

Goal

Stand up the missing DAL tests (north-star: 0 DAL tests today) and turn on GitHub Actions so the suite gates merges. Estimated ~3–4 days.

Context

North-star N3: the DAL has zero tests; Exposed table definitions, repository queries, and the 43-migration schema are validated only incidentally. N2: no CI means no existing test gates anything. This track closes both, building on the TRACK-110 Testcontainers substrate.

Implementation Plan

Phase 1 — DAL suite

Phase 2 — CI activation

Acceptance Criteria

Manual follow-up (not code)